Question: 1) You are completing a project network diagram with the following information. Task A has a duration of 12 days and has Start as its
1) You are completing a project network diagram with the following information. Task A has a duration of 12 days and has Start as its predecessor. Task B has a duration of 20 days and has Start as its predecessor. Task C has a duration of 16 days and has Task A as predecessor. Task D has a duration of 16 days and Task B as predecessor. Task E has a duration of 24 days, and has C and D as predecessors. Task F has a duration of 20 days and has D as its predecessor. The finish milestone has E and F as its predecessors and has zero duration. What is the duration of the project?
a. 64 days
b. 60 days
c. 54 days
d. 56 days
2)You are completing a project network diagram with the following information. Task A has a duration of 12 days and has Start as its predecessor. Task B has a duration of 20 days and has Start as its predecessor. Task C has a duration of 16 days and has Task A as predecessor. Task D has a duration of 16 days and Task B as predecessor. Task E has a duration of 24 days, and has C and D as predecessors. Task F has a duration of 20 days and has D as its predecessor. The finish milestone has E and F as its predecessors and has zero duration. What is the critical path for this network?
a. Start-A-C-E-Finish
b. Start-B-D-F-Finish
c. Start-B-D-E-Finish
d. Start-A-C-E-Finish