Question: 1) You are completing a project network diagram with the following information. Task A has a duration of 12 days and has Start as its

1) You are completing a project network diagram with the following information. Task A has a duration of 12 days and has Start as its predecessor. Task B has a duration of 20 days and has Start as its predecessor. Task C has a duration of 16 days and has Task A as predecessor. Task D has a duration of 16 days and Task B as predecessor. Task E has a duration of 24 days, and has C and D as predecessors. Task F has a duration of 20 days and has D as its predecessor. The finish milestone has E and F as its predecessors and has zero duration. What is the duration of the project?

a. 64 days

b. 60 days

c. 54 days

d. 56 days

2)You are completing a project network diagram with the following information. Task A has a duration of 12 days and has Start as its predecessor. Task B has a duration of 20 days and has Start as its predecessor. Task C has a duration of 16 days and has Task A as predecessor. Task D has a duration of 16 days and Task B as predecessor. Task E has a duration of 24 days, and has C and D as predecessors. Task F has a duration of 20 days and has D as its predecessor. The finish milestone has E and F as its predecessors and has zero duration. What is the critical path for this network?

a. Start-A-C-E-Finish

b. Start-B-D-F-Finish

c. Start-B-D-E-Finish

d. Start-A-C-E-Finish

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!