Question: 1. You are considering a new project. The project has projected depreciation of $720, fixed costs of $6,000, and total sales of $11,760 at a
1. You are considering a new project. The project has projected depreciation of $720, fixed costs of $6,000, and total sales of $11,760 at a sales quantity of 300 units. The variable cost per unit is $17.40. What is the accounting break-even level of production?
A. 308.26
B. 300.64
C. 297.69
D. 311.60
2. A project has been assigned a discount rate of 12 percent. If the project starts immediately, it will have an initial cost of $480 and cash inflows of $350 a year for three years. If the start is delayed one year, the initial cost will rise to $520 and the cash flows will increase to $385 a year for three years. What is the value of the option to wait?
A. $0.20
B. $1.08
C. $1.67
D. $0.70
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
