Question: 1 . You are supposed to install lay CMUs. Estimated quantity: 2 0 0 0 CMUs number of installed CMUs: 4 0 0 CMUs What

1.You are supposed to install lay CMUs.
Estimated quantity: 2000 CMUs
number of installed CMUs: 400 CMUs
What is the percent complete?
Put only value in percentage.
2.For the safety inspection, you made a 12-month contract, whose budget is $24,000.
After 6 months, you paid $15,000.
What is the percent complete applying the actual cost approach?
Put only value in percentage.