Question: 1) Your team has identified over 100 risks associated with your project. The next step is to ____________________. a) Mitigate all of the risks b)
1) Your team has identified over 100 risks associated with your project. The next step is to ____________________.
a) Mitigate all of the risks
b) evaluate each of the risks and determine the impact if it occurs
c) develop a plan for each of the risks you have identified
d) begin implementing the project and watch for any of the risks you have identified
2) Planning for risk management begins only when the implementaiton phase has begun.
a) True
b) False