Question: 10 2 points Additional Algo 19-2 Early Finish Time The network diagram and task times for a project are shown below. A A A4
10 2 points Additional Algo 19-2 Early Finish Time The network diagram and task times for a project are shown below. A A A4 A5 eBook A3 Print Task Duration (days) A1 9 References A2 5 A3 9 24 A5 8 1 What is the early finish time for activity As? days