Question: 10) Assuming that the Critical Path for the given activity times is B-E-G-H-I. calculate the expected time of completion of all the project activities and

10) Assuming that the Critical Path for the given
10) Assuming that the Critical Path for the given activity times is B-E-G-H-I. calculate the expected time of completion of all the project activities and project Standard Deviation. Also, compute the values of completion time range for Activity H at 68.27% probability Pessimistie time Most likely time Immediate Optimistic Activity Predecessors time B 10 B 8 D 14 E B,C 18 F DE 12 G F H G 15 G H 17 19 21 18 26 20 19 22 25 15 17 15 22 17 15 18 20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!