Question: 10 b points Additional Algo 19-5 Slack Time The network diagram and task times for a project are shown below. A2 A A4 eBook
10 b points Additional Algo 19-5 Slack Time The network diagram and task times for a project are shown below. A2 A A4 eBook A3 Print Task Duration (days) A1 5 References A2 9 A3 3 A4 A5 3 8 44 What is the slack for activity A2? days