Question: 10 Check my work 2 Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be

10 Check my work 2 Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) 2 points Project Y Time: Cash flow:$9,000 $3,550 $4,380 $1,720 $500 Skipped NPV eBook Hint Should the project be accepted or rejected? Print accepted References rejected