Question: 10, *Given the time-phased work packages and network, complete the baseline budget 288 Chapter 8 Scheduling Resources and Costs form for the project. 4 8

10, *Given the time-phased work packages and network, complete the baseline budget 288 Chapter 8 Scheduling Resources and Costs form for the project. 4 8 Legend 2 2 ES ID EF 6 4 10 0 4 SL SL 1 1 10 F 12 LS DUR LF 1 4 5 5 D 10 o 0 0 0 10 2 12 5 5 10 0 B 5 0 0 Cost by Week 0 5 5 5 E 8 A 10 10 10 10 2 2 B 8 4 8 4 7 8 3 10 12 12 12 Budget ID 0 1 2 3 4 5 6 7 8 9 10 11 12 D 6 2 NNN 2 6 A 40 E 8 8 B 32 F 20 20 C 48 D 18 E 28 F 40 Total 206 Cumulative