Question: 10. Let us consider two projects: C and D, both need $10 million investment each. Project C generates $15 million in Year 1 and $10
10. Let us consider two projects: C and D, both need $10 million investment each. Project C generates $15 million in Year 1 and $10 million in Year 2. Project D generates 0 in Year 1 and $30 million in Year 2. You can verify that: Project C has NPV of $11.9 million at 10% discount rate and IRR of 100%. Project D has NPV of $14.8 million and IRR of 73.2%. a. What project do you take based on the IRR decision rule? b. What project do you take based on the NPV decision rule? c. Do you get the same decision under both rules? If not why? Which project do you ultimately decide to do?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
