Question: 10. LO 8.2When is the material quantity variance favorable? when the actual quantity used is greater than the standard quantity when the actual quantity used
10. LO 8.2When is the material quantity variance favorable?
- when the actual quantity used is greater than the standard quantity
- when the actual quantity used is less than the standard quantity
- when the actual price paid is greater than the standard price
- when the actual price is less than the standard price
12. LO 8.3What are some possible reasons for a labor rate variance?
- hiring of less qualified workers
- an excess of material usage
- material price increase
- utilities usage change
14. LO 8.3When is the labor rate variance favorable?
- when the actual quantity used is greater than the standard quantity
- when the actual quantity used is less than the standard quantity
- when the actual price paid is greater than the standard price
- when the actual price is less than the standard price
16. LO 8.3When is the direct labor time variance favorable?
- when the actual quantity used is greater than the standard quantity
- when the actual quantity used is less than the standard quantity
- when the actual price paid is greater than the standard price
- when the actual price is less than the standard price
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock