Question: 10.With respect to a Major Capability Acquisition program's funding profile, which possibility would VIOLATE funding policies? Using RDT&E dollars to fund design and build of
10.With respect to a Major Capability Acquisition program's funding profile, which possibility would VIOLATE funding policies? Using RDT&E dollars to fund design and build of pre-production test articles (prototypes) Using procurement funds to buy initial spares for deployed systems Using procurement funds in EMD to fund long-lead items for production units (not needed until Production) Using O&M dollars to fund a design change prior to Milestone C