Question: 10.You are the project manager for a hardware project and have just left a discussion with your finance partner with the latest financial metrics. Actual
10.You are the project manager for a hardware project and have just left a discussion with your finance partner with the latest financial metrics. Actual cost is $2,000,000, planned value is $2,250,000, and CPI is 1.5. Which statement below is correct? Group of answer choices
1.The project is ahead of schedule and under budget.
2.The project is behind schedule and over budget.
3.The project is ahead of schedule and over budget.
4.The project is behind schedule and under budget.