Question: : 11 10 11 7 A , , D, E 5 a) The theoretical minimum number of workstations = (round your response up to the

: 11 10 11 7 A , , D, E 5 a) The theoretical minimum number of workstations = (round your response up to the next whole number). b) The assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) Task Workstation # B Station 4 Station 3 . E Station 2 Station 5 F Station 1 Were you able to assign all the activities to workstations equivalent to the theoretical minin Station 6 c) The efficiency of the assembly line =% (enter your response as a percentage rounded to one decimal place). Enter your answer in each of the answer boxes