Question: 11. Based on the graph below a. At the time of the dotted line is the project over budget, on budget, or under budget, and
11. Based on the graph below
a. At the time of the dotted line is the project over budget, on budget, or under budget, and how do you know? (3 points)
b. At the time of the dotted line, is the project ahead of schedule, on schedule, or behind schedule, and how do you know? (3 points)