Question: 11 e to A project manager is working on a project to scale an operation globally. This endeavor required multiple interviews with various stakeholders. During
11 e to A project manager is working on a project to scale an operation globally. This endeavor required multiple interviews with various stakeholders. During the user story creation phase, the product owner met with multiple stakeholders who had different opinions about the requirements. How go should the project manager address this situation? bl A. Ask the product owner to create the backlog. B. Use a voting system for stakeholders. BE C. Perform a stakeholder identification analysis. D. Limit the participation from stakeholders