Question: 11) Project L requires an initial outlay at t = 0 of $55,000, its expected cash inflows are $13,000 per year for 9 years, and
11)

Project L requires an initial outlay at t = 0 of $55,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 14%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $