Question: 11- While planning for your project as the project manager, you realized that your project has 4 critical paths. Which of the following BEST describes
11- While planning for your project as the project manager, you realized that your project has 4 critical paths. Which of the following BEST describes how it is going to affects your project? A. Critical path - means it needs more people B. Critical path - means it makes project more expensive C. Critical path - means it increases the project risk D. Critical path - means it makes it easier to manage E. None of the above 12- Sam has given commitment to the client that project will be completed on day 30 . The project has 10 activities and 15 resources are assigned to it. The critical path has duration 25 days and 12 activities. What is the project float? A. 5 Days B. 0 Days C. 3 Days D. 6 Days