Question: 11. Your Contract = $1M + $10,000 for every month early the project is finished (not exceeding $30,000 ceiling) You completed this contract in 300

11. Your Contract = $1M + $10,000 for every month

11. Your Contract = $1M + $10,000 for every month early the project is finished (not exceeding $30,000 ceiling) You completed this contract in 300 days instead of 360 days that was in your schedule. Show your Calculation