Question: 11.0 The charge that is most likely a fixed cost is for: Select one: a. Materials. b. Equipment rental. c. Direct labor. d. Utilities. 12.0

11.0 The charge that is most likely a fixed cost is for:

Select one:

a. Materials.

b. Equipment rental.

c. Direct labor.

d. Utilities.

12.0 If it takes 40 hours to complete the first unit and the company knows from experience that the learning rate should be 0.80, how fast can they be expected to finish all twelve units?

Select one:

a. 18 hours

b. 289 hours

c. 264 hours

d. 316 hours

13.0 A budgeting method that assigns costs first to activities and then to projects based on each project's use of resources is:

Select one:

a. Activity-based budgeting.

b. Zero-based budgeting.

c. Top-down budgeting.

d. Bottom-up budgeting

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!