Question: 11-15. A marketing firm is developing a new Web-based media campaign for a client. The following table describes the relationships among the activities that need
11-15. A marketing firm is developing a new Web-based media campaign for a client. The following table describes the relationships among the activities that need to be completed.
| Activity | Immediate Predecessors | Time (Days) |
| A | - | 4 |
| B | A | 6 |
| C | B | 12 |
| D | B | 11 |
| E | D | 9 |
| F | D | 8 |
| G | D | 10 |
| H | C | 5 |
| I | C | 7 |
| J | E,F,G | 4 |
| K | H,I | 9 |
- Develop a project network for this problem.
- Determine the ES, EF, LS, LF, and slack time for each activity. Also determine the total project completion time and the critical path(s). Please Use Excel to do step by step to get these answers.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock