Question: 12 & 13 please Questions 12-14 are based on the following information. Given the following structure, the processing times are 4 for activity a, 5

12 & 13 please 12 & 13 please Questions 12-14 are based on the
12 & 13 please Questions 12-14 are based on the
Questions 12-14 are based on the following information. Given the following structure, the processing times are 4 for activity a, 5 for activity b, and 9 for activity c. Activity a is the beginning activity and activities b and c are ending activities. . C + Question 12 1 pts What is the earliest finishing time (EF) for activity a? None of the answers is correct 09 04 OO Question 13 1 pts What is the latest start time (LS) for activity b? 13 09 04 8