Question: 12 When the budgets for all the work packages are summed, A B D funds for all conceivable issue they cannot exceed the total project

12 When the budgets for all the work packages are summed, A B D funds for all conceivable issue they cannot exceed the total project budgeted cost. if the total is too low then extra non-project expenses should be added. they should ceed the amount of funds available. if the total is too high then the amounts should be force-fitted into the customer's budget. 1 Point