Question: 12.3 Which Project Deliver system is based on a contractual, collaborative arrangement of the major project stakeholders early in the process that promotes a best
-
12.3 Which Project Deliver system is based on a contractual, collaborative arrangement of the major project stakeholders early in the process that promotes a best for project thinking and shares risks and rewards?
Design-Build
Design-Bid-Build
Agency
Integrated Delivery
10 points
QUESTION 2
-
12.1 In which Project Delivery system does the owner have independent contracts with the Architect/Engineer and the contractor?
Design-build
Agency
Integrated
Design-Bid-Build
10 points
QUESTION 3
-
12.2 In the Agency Project Delivery system, who does the General Contractor report to?
Architect
Owner
Construction Manager
Himself