Question: 12.Compute the payback statistic for Project B and decide whether the firm should accept or reject the project with the cash flows shown as follows
12.Compute the payback statistic for Project B and decide whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 12 percent and the maximum allowable payback is three years.
Project B
Time
0
1
2
3
4
5
Cash Flow
-$11,000
$3,350
$4,180
$1,520
$0
$1,000
13.Payback Compute the payback statistic for Project A and recommend whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent and the maximum allowable payback is four years.
Project A
Time
0
1
2
3
4
5
Cash Flow
-$1,000
$350
$480
$520
$300
$100
14.IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent.
Project E
Time
0
1
2
3
4
5
Cash Flow
-$1,000
$350
$480
$520
$300
$100
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
