Question: 1.3 The following five (5) jobs are ready for processing at an assembly plant in Rosslyn. The critical ratio technique and earliest due date technique

1.3 The following five (5) jobs are ready for processing at an assembly plant in Rosslyn. The critical ratio technique and earliest due date technique have been selected to schedule the jobs. 1.3.1 Assuming that today is day 10 on the planning calendar, determine the schedule in which the jobs must be processed and the average job lateness using the two techniques. Show full calculations by completing the table below. (3) 1.3.2 Determine the average job lateness of the two techniques. Show full calculations by completing the table below