Question: 13. The network method works better than a Gantt chart on complex projects. True False 14. The Gant charts conform with Pareto chart logic. True
13. The network method works better than a Gantt chart on complex projects.
True
False
14. The Gant charts conform with Pareto chart logic.
True
False
15. In scheduling, early start, late start, early finish and late finish times for each activity can be computed by means of a forward pass and a backward pass through the network.
True
False