13-1 NPV with Normal Cash Flows
Compute the NPV for Project M and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. (LG13-3)
Project M
Time: 0 1 2 3 4 5
Cash flow -$1,000 $350 $480 $520 $600 $100