Question: 14. Data on critical path activities for a project is below. Applying PERT model, what is the 93rd percentile of path duration (round up


14. Data on critical path activities for a project is below. Applying 

14. Data on critical path activities for a project is below. Applying PERT model, what is the 93rd percentile of path duration (round up to integer)? (15 points) Activity G K P Optimistic Duration 6 8 12 9 14 20 15 19 26 Most Likely Duration Pessimistic Duration