Question: 14. Data on critical path activities for a project is below. Applying PERT model, what is the 93rd percentile of path duration (round up
14. Data on critical path activities for a project is below. Applying PERT model, what is the 93rd percentile of path duration (round up to integer)? (15 points) Activity G K P Optimistic Duration 6 8 12 9 14 20 15 19 26 Most Likely Duration Pessimistic Duration
Step by Step Solution
3.45 Rating (142 Votes )
There are 3 Steps involved in it
To find the 93rd percentile of path duration using the PERT model we need to first calculate the exp... View full answer
Get step-by-step solutions from verified subject matter experts
