Question: 14 Figure 1 Task time estimates for the modification of an assembly line at Jim Goodal's Carbondale, Illinois, laders are as follows: Immediate Predecessorts) Time

14
14 Figure 1 Task time estimates for the
Figure 1 Task time estimates for the modification of an assembly line at Jim Goodal's Carbondale, Illinois, laders are as follows: Immediate Predecessorts) Time Activity in hours) A 60 B 67 C 40 D BO E 5.1 F 50 BC B,C D EF This were contains only part a) The corect precedence diagram for the project is shown in Figure 2 od 3 Figure 3