Question: (14 points total) 3. Information is shown below for the last 5 activities in a project with many activities. The network corresponding to this is

 (14 points total) 3. Information is shown below for the last

(14 points total) 3. Information is shown below for the last 5 activities in a project with many activities. The network corresponding to this is shown below and in the (M,N,O and P are activities before Q and R ). The table also shows the earliest start (ES) times for activities Q and R. (8 pts.) a) Fill in the table above with the earliest start (ES) and earliest finish (EF) times, the latest start (LS) and latest finish (LF) times and the slac for activities Q,R,S,U,V and W. (You can also fill in the boxes in the network with ES, EF, LS LF if you wish.) (2 pt.) b) What is the minimum (earliest) completion time of the project? (2 pt.) c) Which activities are on the critical path? (2 pt.) d) Which activity (or activities) have the greatest slack and how large is that slack

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!