Question: 14 saved Saved What cycle time would match capacity and demand if demand is 162 units a day, there are 2 shift(s) of 447 minutes

14 saved Saved What cycle time would match

14 saved Saved What cycle time would match capacity and demand if demand is 162 units a day, there are 2 shift(s) of 447 minutes each and workers are given four 40 minute breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.) Cycle time minutes per cycle

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!