Question: 14 saved Saved What cycle time would match capacity and demand if demand is 162 units a day, there are 2 shift(s) of 447 minutes

14 saved Saved What cycle time would match capacity and demand if demand is 162 units a day, there are 2 shift(s) of 447 minutes each and workers are given four 40 minute breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.) Cycle time minutes per cycle