Question: 14&15 If a project has five critical path activities and the project completion time variance is calculated to be 4 , the project's completion time

14&15 14&15 If a project has five critical path
If a project has five critical path activities and the project completion time variance is calculated to be 4 , the project's completion time standard deviation is 2 16 20 10 Question 15 4 pts If an activity whose normal duration is 13 days can be shortened to 11 days for an added cost of $1,500, what is the crash cost per period? $1,500 $13,000 $500 $750