Question: 14.Compute the NPV for Project X with the cash flows shown below if the appropriate cost of capital is 8 percent. Time: 0 1 2

14.Compute the NPV for Project X with the cash flows shown below if the appropriate cost of capital is 8 percent. Time: 0 1 2 3 4 5 Cash flow: -135 -135 0 220 195 170

$160.81 $433.67 $173.67 $154.19