Question: 14.what is the correct answer? Assume that the free float of an activity is 2 units. If this activity is started 1 unit later than

14.what is the correct answer?
Assume that the free float of an activity is 2 units. If this activity is started 1 unit later than the earliest starting time (if it is delayed by 1 unit),... Note: This is a multiple response question. You may mark more than one correct choice if any. a) the project will be completed 1 unit later. b) the free float of all activities following this activity is reduced by 1 unit. c) No other activity in the project is affected. d) the project will be completed on timeStep by Step Solution