Question: 14.what is the correct answer? Assume that the free float of an activity is 2 units. If this activity is started 1 unit later than

14.what is the correct answer? Assume that the

14.what is the correct answer?

Assume that the free float of an activity is 2 units. If this activity is started 1 unit later than the earliest starting time (if it is delayed by 1 unit),... Note: This is a multiple response question. You may mark more than one correct choice if any. a) the project will be completed 1 unit later. b) the free float of all activities following this activity is reduced by 1 unit. c) No other activity in the project is affected. d) the project will be completed on time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!