Question: 15 18 Moving to another question will save this response Question 21 If an activity whose normal duration is 21 days can be shortened to

15 18 Moving to another question will save this
15 18 Moving to another question will save this response Question 21 If an activity whose normal duration is 21 days can be shortened to 9 days for an added cost of $6,542, what is the crash cost per period normal duration crash duration cost to crash 21 days 9 days $6,542 A Moving to another question will save this response