Question: 15) Consider a capital budgeting example with five projects from which to select. Let x1 = l if project a is selected, O if not,

15) Consider a capital budgeting example with

15) Consider a capital budgeting example with five projects from which to select. Let x1 = l if project a is selected, O if not, for a = 1, 2, 3, 4, 5. Projects cost $100, $50, $150, $75, and $150, respectively. The budget is $450. Write the appropriate constraint for the following condition: a. Choose no fewer than 4 projects. b. Choose projects with respect to the budget limit