Question: 15 Marks Question 1 Let the following table represents theactivities of a project to be implemented. When solving thisquestion use the CPM method. Activity A

15 Marks Question 1 Let the following table represents theactivities of a project to be implemented. When solving thisquestion use the CPM method. Activity A B ? D E Duration (Weeks) 24 1 6 3 Imme 1 answer