Question: 1.5 points Save Answer Question 5 Stones Manufacturing sells a marble slab for $1500. Fixed costs are $31,000, while the variable costs are $450 per
1.5 points Save Answer Question 5 Stones Manufacturing sells a marble slab for $1500. Fixed costs are $31,000, while the variable costs are $450 per slab. The company currently plans to sell 240 slabs this month. What is the margin of safety assuming 75 slabs are budgeted? $207,714.286 $315,714,286 $31,000 $68,214.2857