15.12 A Northern British Columbia lumberyard has four jobs on order, as shown in the following table.
Fantastic news! We've Found the answer you've been seeking!
Question:
15.12 A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. Job Due Date Remaining Time (days) A 212 6 B 209 3 C 208 3 D 210 8 In what sequence would the jobs be ranked according to the following decision rules: a) FCFS b) SPT c) LPT d) EDD e) Critical ratio Which is best and why? Which has the minimum latenes