Question: 16 17 18 Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $5,000 per year
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $41,500, and its expected cash flows would be $8,300 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. 3 b. Both Projects S and L, since both projects have IRR's > 0. c. Project S, since the NPVs > NPVL, d. Project L, since the NPVL > NPVS. e. Neither Project Snor , since each project's NPV
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
