Question: 16. Based on Analogy-Based Effort Estimation knowing that a new Project Y estimated to be 8,000 (LOC), while an old Project x with a 16,000

 16. Based on Analogy-Based Effort Estimation knowing that a new Project

16. Based on Analogy-Based Effort Estimation knowing that a new Project Y estimated to be 8,000 (LOC), while an old Project x with a 16,000 line of code (LOC) and a 12 person-month of effort. Calculate the KLOC per person-month of the new project? (show all the steps required to solve it) LS (4 Points) Enter your