Question: 16. Consider the network in Problem 6, but with the following new time estimates for each activity: Activity 1 Time Estimates (mo.) a m b

16. Consider the network in Problem 6, but with

16. Consider the network in Problem 6, but with the following new time estimates for each activity: Activity 1 Time Estimates (mo.) a m b 4 8 12 6 10 15 2 10 14 1 4 13 2 3 4 5 3 6 9 6 3 6 18 7 2 8 12 8 9 15 22 21 9 5 12 10 7 20 25 11 5 6 12 20 12 3 8 Determine the following: a. Expected activity times b. Earliest activity times c. Latest activity times d. Activity slack e. Critical path f. Expected project duration and variance