Question: 16)You are managing a software project that started six months ago. The project team is comprised of 20 internal employees and three personnel from different
16)You are managing a software project that started six months ago. The project team is comprised of 20 internal employees and three personnel from different software vendors. To understand the status of the project, which of the following reports is most useful?
a. Work performance data
b. EAC and TCPI
c. Status reports
d. Progress reports
18)What is the generally correct order of activities in the Project Human Resource Management knowledge area?
a. Plan Human Resource Management, Develop Project Team, Acquire Project Team, Manage Project Team
b. Develop Project Team, Acquire Project Team, Plan Human Resource Management, Manage Project Team
c. Acquire Project Team, Plan Human Resource Management, Develop Project Team, Manage Project Team
d. Plan Human Resource Management, Acquire Project Team, Develop Project Team, Manage Project Team
19)Your project team is working on a software project with over 2 million lines of code and has just randomly selected a number of lines of code for inspection. What quality technique are they using?
a. Random inspection
b. Design of experiments
c. Benchmarking
d. Statistical sampling
23)You are showing your team the relative interest and power each identified stakeholder has in your project. What is the BEST way to show this information?
a. Stakeholder register template
b. Control chart
c. Power/interest grid
d. Salience model