Question: 17 ) Barker Inc. uses the weighted-average method in its process costing system. The following data concern the operations of the company's first processing department
17) Barker Inc. uses the weighted-average method in its process costing system. The following data concern the operations of the company's first processing department for a recent month.
|
| Work in process, beginning: |
|
|
| Units in process...................................................... | 800 |
|
| Percent complete with respect to materials.......... | 70% |
|
| Percent complete with respect to conversion....... | 10% |
|
|
Costs in the beginning inventory: |
|
|
| Materials cost......................................................... | $ 1,750 |
|
| Conversion cost...................................................... | $ 3,000 |
|
|
|
|
|
| Units started into production during the month....... | 19,000 |
|
| Units completed and transferred out........................ | 17,800 |
|
|
|
|
|
| Costs added to production during the month: |
|
|
| Materials cost......................................................... | $ 60,000 |
|
| Conversion cost...................................................... | $ 357,000 |
|
|
|
|
|
| Work in process, ending: |
|
|
| Units in process...................................................... | 2,000 |
|
| Percent complete with respect to materials.......... | 60% |
|
| Percent complete with respect to conversion....... | 10% |
Required to solve:
a. What is the equivalent units of production?
b. What is the costs per equivalent unit?
c. What is the cost of ending work in process inventory?
d. What is the cost of the units completed and transferred to the next department?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts