Question: 17. This (often secondary) precedence network type uses arrows or ares to visually represent tasks and nodes to visually represent events or milestones. a. precedence

17. This (often secondary) precedence network type uses arrows or ares to visually represent tasks and nodes to visually represent events or milestones. a. precedence diagram b. activity on arc (AOA) c. activity on node (AON) d. nodes and arrows graphic