Question: 17) Your boss is the project manager for a large contract assembly plant. She tells you that the learning rate for Product M is 0.80
17) Your boss is the project manager for a large contract assembly plant. She tells you that the learning rate for Product M is 0.80 and that the first unit took 29.82 hours. Suppose your company has 600 hours available to build Product M, how many units could you produce? Answer with a whole number (no decimals)