Question: 18 A forecast based on the previous forecast plus a percentage of the forecast error is: Select one: a. an associative forecast. b. a naive

18 A forecast based on the previous forecast plus a percentage of the forecast error is: Select one: a. an associative forecast. b. a naive forecast. c. a simple moving average forecast. d. an exponentially smoothed forecast. e. a centred moving average forecast.