18) Given the project within the table below,
18) Given the project within the table below, SOLVE THIS PROBLEM ON YOUR OWN AS A DRAFT and answer the following question. What is the probability that the project will be completed in 30 hours if the standard deviation is 2 hours? 10 Points => 1 of 1 oC Activity A B D E F G Duration (hours) 5 4 10 7 2 2 7 Immediate Predecessors None None None B,C D DE AF Download file 82.1596 97.32% 87.13% 78.54%