Question: 18 - Use this information to answer the question that follow. The standard costs and actual costs for factory overhead for the manufacture of 2,600
18 - Use this information to answer the question that follow. The standard costs and actual costs for factory overhead for the manufacture of 2,600 units of actual production are as follows:
| Standard Costs | |
| Fixed overhead (based on 10,000 hours) | 3 hours per unit @ $0.77 per hour |
| Variable overhead | 3 hours per unit @ $1.92 per hour |
| Actual Costs | |
| Total variable cost, $17,900 | |
| Total fixed cost, $7,800 | |
The variable factory overhead controllable variance is
a.$2,924 favorable
b.$0
c.$2,339 favorable
d.$2,924 unfavorable
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
